Tuesday 23 August 2016

Housing Land Supply - North Wales.

We've alluded to problems of Housing Land Supply in previous posts.

Welsh Government Policy requires a Council to demonstrate a 5 year supply of housing land  using something called the "residual method".  In simple terms this can be expressed as:-

Number of houses planned in Development Plan minus the number of units already completed and with permission to be built since the plan began, sprinkle a little jiggery pokery for units which may or may not be predicted as being completed within 5 years to give you the "balance to be built".  Divide that by the number of years the plan has left until its end date to give an annual requirement and multiply by 5.  Simples eh?

August is a fascinating time in consultancy whilst those of us not sunning ourselves on the beach await release of the latest Joint Annual Housing Land Supply reports. 

How are things currently looking?.  

*Anglesey: (stopped UDP)..  Cannot demonstrate a supply as no adopted plan.  1022 units available as at Feb 2016.  
Conwy: (adopted LDP).  3.7 years (August 2016).  Annual delivery requirement to meet LDP target has risen from an annual average rate of 420 units to 618.  
Denbighshire: (adopted LDP).   2.02 years (July 2016).  Annual delivery requirement to meet LDP target has risen from 500 units to 1055.
Flintshire. (UDP Expired 2015).  Cannot demonstrate a supply with no adopted plan.  LDP predicted adoption mid 2019.   3076 units predicted available.   
*Gwynedd:  (Adopted UDP).  2.9 years.  (August 2016).  Annual delivery requirement to meet UDP target has risen from 278 to 538.
Wrexham: (UDP Expired).  Cannot demonstrate a  supply with no adopted plan.  LDP predicted mid 2019.  1274 units available as at April 2015.  LPD adopted predicted mid 2018. 

* The joint Anglesey/Gwynedd LDP is moving toward examination in the autumn.  The overall target figure is 7902 (527pa) so it looks as though the LDP will be adopted with an immediate shortage and will be playing catch up straight away as the annual average rate of completions is expected to be 254 and 272 for Anglesey and Gwynedd respectively.  Neither rate has been achieved.

Using a relatively crude measure such as the residual method perhaps magnifies the effects of undersupply (or rather under delivery) during say a period of low build rates or economic downturn.  However its also reasonable that would smooth out over the 15year lifetime of a plan.  However its also the case that no North Wales LPA has witnessed housing completions  anywhere near its annual target in any recent year.  That merely compounds the problem by increasing the residual gap ever more.  Therein lies the challenge.

We may  do some further analysis down the line but the basic conclusions are:
  • No North Wales Council has a five year housing supply and so must be open to additional housing proposals which meet the the PPW objectives of delivering sustainable development.
  • The annual housing requirement for each authority is increasing year on year and we simply predict the gaps will get bigger unless more houses are actually built.
  • The delivery of housing is nowhere near the levels required. 
In a future post we might look to some of the problems and thoughts on solutions.

Wednesday 3 August 2016

Development Management Frontloading - The reality of the New World

Yesterday brought the first post 01 Aug phone call about a new major development in Wales.   We've been working flat out to get those we can sorted before the deadline.

By "major" we mean a warehouse buidling extension of some 1200m2 on his 1.5ha site.

Ive this afternoon let the client know pre-application consultation requirements.

Lets run through the supporting info briefly:

1.  Existing and proposed site, elevation and floorplans. (at least 6 drawings). Planning forms
2. Flood Consequences Assessment. site in Zone C1.
3. Known Great Crested Newts in locality. Phase 1 Eco, potentially Phase 2.
4. Design and Access Statement.
5. Planning Statement. 
6. Building will be close to Adjacent trees and boundary hedgerow.  Arboricultural report.

Ive advised him to take advantage of the statutory, pre-application service the Council offers initially ( £600 stat fee).  

He now must also consult in advance of making any planning application these Community and Specialist consultees:

1. Cheshire West Council (site abuts Cheshire Boundary)
2. The Welsh Ministers- The site is 1.5 ha and lies within 5KM of a scheduled ancient monument. 
3. The Community Council.
4. County Councillors X 3.
5.The Highway Authority.
6 National Resources Wales and
7.  4 no adjacent occupiers and 

A site notice is to be displayed for 28 days advising where the documents can be viewed in that period. We've yet to identify a community building (which might be open!!) where the application documents can be displayed publicly.  

Lets assume this fairly modest warehouse extension wont justify  www.modestfactoryextension.co.uk.  So he probably has to provide hard copies of it all, those 8.  I expect public sector consultees will accept emails or CD,  

I'm now going to work some times (and therefore fee indication) on these requirements.      

And then at the end of this, collate a Planning Application Consultation Report to submit alongside the application. 

The silence on the end of the line was deafening.  He only wants to store some additional furniture.  

At this very modest scale of "major" development I'm not yet sure that Welsh Government grasps the "risk" doing all this in advance creates for a business.   Time will tell.  It will also tell if he  commits.